What must be included in as-built drawings provided to the local agency?

  1. Details of the excavation machinery

  2. The actual location of the tanks and piping

  3. The costs associated with installation

  4. Future maintenance plans

The correct answer is: The actual location of the tanks and piping

As-built drawings serve as a record of a construction project after it has been completed, reflecting any changes made during construction. When it comes to the information required in as-built drawings provided to the local agency, the actual location of the tanks and piping is crucial. These drawings should accurately depict the final locations and configurations of the infrastructure that has been installed, compared to the initial plans. This facilitates future inspections, maintenance, and potential renovations, ensuring that all parties involved have the most current information regarding the project. It helps in understanding how the project interfaces with other existing services and structures, which is vital for safety and compliance with local regulations. The other options, while they may be relevant in different contexts or phases of project management, do not hold the same necessity in as-built drawings. Detailed information about excavation machinery, costs associated with installation, and future maintenance plans are generally not included in as-built documentation. Instead, those aspects would be covered in other project documentation or reports rather than as-built drawings.