What is one of the requirements for using vadose zone monitoring?

  1. It must be conducted by the local agency

  2. It must comply with Title 23 section 2647

  3. It can be conducted once a year

  4. It does not require any reporting to the local agency

The correct answer is: It must comply with Title 23 section 2647

The requirement for using vadose zone monitoring in California includes compliance with Title 23, section 2647. This regulation establishes the standards and guidelines for monitoring activities related to the vadose zone, which is the area of soil above the groundwater table. Compliance with this regulation ensures that monitoring is conducted effectively and that the data gathered can be utilized for assessing environmental impacts, managing water resources, and maintaining groundwater quality. This regulation typically outlines the protocols to be followed, the frequency of monitoring, and the need for proper reporting of the findings. Therefore, meeting the standards set forth in Title 23, section 2647 is essential for any vadose zone monitoring activities to ensure they align with regulatory requirements and best practices. Understanding these regulations is crucial for anyone involved in environmental monitoring and management in California.